During iteration planning, Team A identifies an important deliverable that depends on a deliverable from Team B. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Notify Team B of the dependency and confirm the deliverable is planned.
Why this is the answer
The project manager should notify Team B of the dependency and confirm the deliverable is planned to ensure alignment and avoid potential delays. This proactive communication is crucial in agile environments to manage inter-team dependencies effectively. Asking Team B to focus solely on their backlog without acknowledging the dependency could lead to Team A being blocked. Merging teams is an extreme measure and generally unnecessary for managing a single dependency. Asking Team B to start immediately might disrupt their current sprint goals and priorities without proper coordination. The best approach is to communicate and collaborate to integrate the dependency into Team B's plan.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed