During iteration two of a project with teams A and B, two critical activities from team A must start in iteration four but depend on an activity from team B that has not been prioritized. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Ensure team B prioritizes the dependent activity in iteration three..
Why this is the answer
The project manager should ensure team B prioritizes the dependent activity in iteration three. This proactive approach addresses the dependency before it becomes a critical path issue. By having team B complete the activity in iteration three, the critical activities for team A can start as planned in iteration four, preventing delays. Canceling the current iteration is an extreme measure that would disrupt progress and waste effort. Including the dependent activity in the current iteration for team B might overload them or disrupt their planned work, as it wasn't prioritized. Assigning team A's critical activities to team B in iteration two is not feasible, as team B may lack the expertise or capacity, and it doesn't resolve the underlying dependency issue.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed