During planning, the project manager is told one activity cannot start until another department implements a required IT system. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Document the dependency in the project schedule..
Why this is the answer
The project manager should document the dependency in the project schedule. This is a fundamental planning activity that ensures all known constraints and relationships between activities are formally recorded. Documenting it allows for proper scheduling, resource allocation, and risk management. Fast-tracking is a schedule compression technique, not a primary response to a newly identified dependency, and might not be feasible or appropriate without further analysis. Performing integrated change control is premature; this is a planning activity, not yet a change request. Asking IT to prioritize the system is an action that might follow documentation and analysis, but the immediate and most appropriate step is to formally record the dependency.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed