During planning the team listed activities and completed sequencing. They discovered a missing dependency between: • Test the product • Release to customer. The quality management plan requires testing before release. How should the project manager record this dependency?
Choose an answer
Tap an option to check your answer.
Correct answer: Finish to start.
Why this is the answer
The correct answer is Finish to Start (FS). This is the most common type of dependency, where the successor activity (Release to customer) cannot start until the predecessor activity (Test the product) is finished. The quality management plan explicitly states that testing must occur before release, directly indicating an FS relationship. Start to Start (SS) would mean "Release to customer" could start as soon as "Test the product" starts, which contradicts the requirement for testing to be completed first. Finish to Finish (FF) would mean "Release to customer" must finish at the same time "Test the product" finishes, which doesn't enforce the prerequisite. Start to Finish (SF) would mean "Release to customer" must finish before "Test the product" can start, which is illogical in this scenario.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed