During product development the project manager observes stakeholder conflicts that delay deliverable and output approvals. Which area should the project manager focus on?
Choose an answer
Tap an option to check your answer.
Correct answer: Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders.
Why this is the answer
The correct answer is revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders. Conflicts and delays in approvals often stem from unmanaged expectations or a lack of understanding from key stakeholders. The stakeholder engagement plan is the primary tool for identifying stakeholders, analyzing their interests, and planning effective engagement strategies. If conflicts are delaying approvals, it suggests that some stakeholders' needs or influence were not adequately addressed, or their engagement strategy is ineffective. Reviewing and updating this plan to specifically target those causing delays is the most direct and effective solution. Reviewing the project management plan to confirm deliverable timing might identify schedule issues but doesn't address the root cause of stakeholder conflict. Increasing the frequency of project updates is a communication tactic, but without addressing underlying engagement issues, it may not resolve conflicts. Reviewing the business case for scope gaps is about project scope, not directly about stakeholder conflict resolution.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed