During project execution, the project manager reviews the issue log and finds high-priority issues that require external domain experts who are not on the team. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the open issues with the issue reporter and issue a change request to hire an external domain expert..
Why this is the answer
The project manager should review the open issues with the issue reporter and issue a change request to hire an external domain expert. This approach ensures that the high-priority issues are addressed by qualified personnel, maintaining project quality and integrity. A change request is necessary to formally introduce new resources and potentially adjust the budget or schedule. Requesting team members to learn new domain knowledge quickly is unrealistic for high-priority issues and could lead to delays or errors. Asking the issue reporter to close the issues without resolution is irresponsible and detrimental to the project. Reducing project scope to avoid the issues is a last resort and should only be considered if other options are unfeasible and after thorough analysis of its impact on project objectives.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed