During project execution the team identified a new opportunity that is outside the project scope. The project manager updated the risk register and escalated the opportunity to a higher level. What should the project manager do next regarding this opportunity?
Choose an answer
Tap an option to check your answer.
Correct answer: Continue to monitor the opportunity..
Why this is the answer
The project manager should continue to monitor the opportunity because, while it's outside the current project's scope, it has been identified and escalated. Monitoring ensures that if conditions change or if the opportunity becomes relevant to future projects or the organization's strategic goals, it can be revisited. "No further action is required" is incorrect because opportunities, even if out of scope, can still hold value and should be tracked. "Share the opportunity with another project" is premature and might not be appropriate without further analysis or organizational guidance. "Establish a contingency reserve" is incorrect; contingency reserves are for known risks with uncertain impacts, not for out-of-scope opportunities.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed