During quality control, the project manager finds the quality management plan lacks how the final user will perceive the product's benefits versus the actual product. What should the project manager do first?
Choose an answer
Tap an option to check your answer.
Correct answer: Submit a change request to analyze a new set of quality tests..
Why this is the answer
The project manager should submit a change request to analyze a new set of quality tests. This is the formal process for addressing a deficiency in a project management plan. The change request allows for proper evaluation of the proposed changes, their impact, and approval before implementation. Asking the product or quality manager directly to add tests bypasses the formal change control process, which is essential for maintaining project integrity and documentation. Letting the product go to market without addressing this gap is reactive and could lead to significant customer dissatisfaction and rework, which is contrary to proactive quality management.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed