During the execution phase, the project manager discovers two team members lack the technical skills needed for upcoming tasks. As a servant leader, what should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Explore a training program that is within the project budget for the team members..
Why this is the answer
As a servant leader, the project manager's primary role is to support and empower the team. Exploring a training program directly addresses the skill gap, develops the team members, and helps the project succeed without resorting to more drastic measures. This aligns with the servant leadership principle of fostering growth and well-being. Recommending self-upskilling places the burden entirely on the team members without active support. Discussing changing team members is a last resort and undermines team stability and morale. Informing the sponsor about a delay without first attempting to resolve the issue internally is premature and reactive, not proactive problem-solving.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed