During the third iteration the sponsor retired and a new sponsor unfamiliar with agile requests more control over the team. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet with the new sponsor to explain the agile approach and how teams self-organize.
Why this is the answer
The project manager should meet with the new sponsor to explain the agile approach and how teams self-organize. This proactive communication helps educate the sponsor on agile principles, such as self-organizing teams and iterative development, which can alleviate concerns about control. It fosters understanding and builds a collaborative relationship. Discussing the request with the team at a daily review meeting is inappropriate as it's a sponsor-level concern requiring direct engagement. Calling an emergency meeting to comply with every request is reactive and undermines agile principles of self-organization and team autonomy. Discussing it at the iteration review is too late for an immediate concern and doesn't directly address the sponsor's need for understanding.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed