During user acceptance testing a defect is found that may seriously affect system performance, and the team says it threatens the delivery date. Which risk management process should be performed?
Choose an answer
Tap an option to check your answer.
Correct answer: Plan Risk Responses, to outline the possible options to bypass the system performance issue.
Why this is the answer
The correct answer is Plan Risk Responses because a significant defect threatening the delivery date requires immediate action to develop strategies for addressing it. This process involves identifying options and actions to enhance opportunities and reduce threats to project objectives. Perform Qualitative Risk Analysis would be done earlier to prioritize risks, but the impact is already known to be serious. Monitor Risks is an ongoing process, but at this stage, the focus is on developing a response, not just monitoring. Perform Quantitative Risk Analysis would quantify the financial or schedule impact, which might be part of understanding the risk, but the primary need here is to plan how to deal with the identified threat.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed