Early in execution, the project manager learns that recent changes to enterprise environmental factors (EEFs) will significantly lower implementation costs and shorten the project schedule. How should the project manager handle this situation?
Choose an answer
Tap an option to check your answer.
Correct answer: Follow the project escalation policy and communications management plan.
Why this is the answer
The correct answer is to follow the project escalation policy and communications management plan. Significant changes to project parameters, even positive ones like lower costs and a shorter schedule, require formal communication and stakeholder engagement. The escalation policy dictates how to report such changes, and the communications management plan outlines who needs to be informed and through what channels. This ensures transparency, allows for informed decision-making by stakeholders, and potentially leads to re-baselining the project. Meeting with the team to spend the budget or retaining unspent funds as management reserve are incorrect because these actions are premature and bypass formal project governance. Allowing extra time is also incorrect as it negates the positive impact of the reduced schedule and could be seen as inefficient.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed