From previous lessons learned, a project manager knows a client is slow to approve documents and often misses agreed timelines. At the kickoff meeting for a new project with the same client, how should the project manager address this issue?
Choose an answer
Tap an option to check your answer.
Correct answer: Agree with the client on acceptable document approval turnaround times..
Why this is the answer
The best approach is to proactively agree on acceptable document approval turnaround times with the client. This sets clear expectations from the start, establishes a baseline for performance, and allows for early negotiation and commitment from the client. Recording the potential for delayed approvals in the risk register is a good step, but it's reactive and doesn't prevent the issue; it only documents it. Informing the client that additional resources will be provided is a concession that might not be necessary or sustainable and doesn't address the root cause of the client's behavior. Reminding the client of their responsibilities is confrontational and less collaborative than seeking agreement on specific timelines.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed