Given the requirements with their anticipated ROI and identified risks plus the analysis details, what should be the priority order in the product backlog?
Choose an answer
Tap an option to check your answer.
Correct answer: Requirement 3, Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2.
Why this is the answer
The correct answer prioritizes items based on their value and risk. Requirement 3 has the highest ROI (100%), making it the top priority. Requirement 1, with a 50% ROI, comes next. Risk 3, with a high impact and probability, is then prioritized to mitigate potential issues early. Requirement 2, having the lowest ROI (20%), follows. Finally, Risk 1 and Risk 2, with lower impact/probability compared to Risk 3, are placed at the end. The other options incorrectly mix requirements and risks without a consistent prioritization strategy or fail to include all relevant items.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed