In a complex development project with many clients and team members, required work has been delayed. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Work with the team to develop a risk response plan..
Why this is the answer
The correct answer is to work with the team to develop a risk response plan. This is the most proactive and effective approach. Delays in required work are a clear indication of a realized risk or an emerging issue that needs a structured response. By collaborating with the team, the project manager leverages their expertise to identify the root causes of the delay and formulate actionable strategies to mitigate its impact, prevent recurrence, or recover the schedule. This aligns with the project manager's role in risk management and problem-solving. Empowering team members is generally good practice but doesn't directly address an existing delay; it's a management style, not a solution to a specific problem. Sending an email to HR is inappropriate as this is a project performance issue, not an HR matter. Informing the project sponsor is necessary, but it's a reporting action, not a problem-solving action. The project manager should first work on a solution before escalating, or at least concurrently with escalation, to provide potential solutions rather than just problems.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed