In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Validate the requirement change with the product owner and development team before changing the scope..
Why this is the answer
The correct answer is to validate the requirement change with the product owner and development team before changing the scope. In an agile or frequently changing environment, new requirements are common. The product owner represents the customer's voice and prioritizes changes, while the development team assesses feasibility and effort. This collaborative approach ensures the change aligns with project goals and is implementable before formally adjusting the scope. Escalating to management immediately is premature; the team needs to understand the change first. Deferring the change without assessment is not a proactive approach in a flexible environment. Asking only the scrum master to assess effort is insufficient; the entire development team's input is crucial for accurate estimation and commitment.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed