In a geographically distributed team a developer is delaying a coding activity that is on the critical path. The delay stems from the developer not understanding customer requirements shared by the off-site team. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Facilitate communication to clarify the requirements..
Why this is the answer
The project manager's primary role is to facilitate project success. In this scenario, the core issue is a lack of understanding of requirements, leading to a critical path delay. Facilitating communication directly addresses this problem by ensuring the developer receives the necessary clarification to proceed. Replacing the developer is a drastic measure that doesn't address the underlying communication breakdown and could introduce further delays and costs. Performing a root cause analysis is a good practice for continuous improvement but is a reactive step that won't immediately resolve the current critical path delay. More frequent performance reviews are not directly related to resolving a technical misunderstanding and could be demotivating.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed