In a software project, the product owner and development team agreed on a sprint backlog where the top priority is a payment module. The team worked on it during the first half of the sprint, but two developers now want to spend the remainder refactoring another feature that may cause future issues. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Remind the developers of the importance of focusing on and meeting the sprint goal..
Why this is the answer
The correct approach is to remind the developers of the importance of focusing on and meeting the sprint goal. In Scrum, the sprint backlog is a commitment to deliver specific functionality that contributes to the sprint goal. Deviating from this agreed-upon work mid-sprint undermines the team's commitment and predictability. While refactoring is valuable, it should be prioritized and planned during sprint planning or as a backlog item for a future sprint, not spontaneously introduced. Allowing the refactoring would compromise the sprint goal. Escalating to functional managers is an overreaction and bypasses the team's self-organizing principles. Praising them for being proactive is inappropriate as it encourages deviation from the sprint commitment.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed