In an agile project, a team member warns they may not complete a task on time, risking a blockage for the team. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Ask the team member to raise the concern at the next daily stand-up.
Why this is the answer
In an agile project, the daily stand-up is the primary forum for team members to communicate progress, discuss impediments, and raise concerns. By asking the team member to raise the issue at the stand-up, the project manager facilitates transparency and allows the entire team to collaboratively find a solution, embodying agile principles of self-organization and collective problem-solving. Emailing all team members bypasses the collaborative nature of the stand-up and might lead to fragmented communication. Reassigning the task without team input can undermine team autonomy and may not address the root cause of the delay. Postponing the task to the next sprint without understanding the impact and exploring immediate solutions can lead to delays and impact sprint goals.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed