In an agile project currently in iteration four of six, a team member leaves the company with no replacement. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Update the issue log and consult the resource management plan to resolve the situation..
Why this is the answer
The project manager should update the issue log and consult the resource management plan because this is the most systematic and comprehensive approach to addressing a critical resource departure. The issue log formally documents the problem, ensuring it's tracked and visible. The resource management plan outlines strategies for acquiring, managing, and releasing project resources, including contingency plans for resource loss. This plan will guide the project manager in identifying potential solutions, such as cross-training, reassigning tasks, or requesting new resources, while considering the project's overall resource strategy. Asking the sponsor for an experienced internal team member is a potential solution, but it's premature without first consulting the established resource plan. Reducing project scope is a drastic measure that should only be considered after exploring other resource solutions and assessing the impact on project objectives. Asking remaining team members to take on extra work can lead to burnout and decreased quality, and it's not a sustainable long-term solution.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed