In an agile project, stakeholders are unhappy because some delivered products do not meet their expectations. When the project manager asks the team about stakeholder expectations, the team only cites the project objective. Besides reminding the team about stakeholder expectations, interest, and influence, what should the project manager do to improve this?
Choose an answer
Tap an option to check your answer.
Correct answer: Teach the team how to use the user persona technique..
Why this is the answer
The user persona technique helps the team understand and empathize with different user types, including their needs, goals, and pain points. This understanding goes beyond a general project objective and allows the team to develop products that better meet specific stakeholder expectations. Creating and using an agile project charter is a good practice for defining project scope and vision, but it may not delve into the detailed expectations of individual stakeholders as effectively as user personas. Using an information radiator is for displaying information, not for analyzing expectations. While face-to-face communication is valuable, simply reminding the team about it doesn't provide a structured technique for understanding nuanced stakeholder expectations.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed