In an agile team using rotating facilitators for the daily scrum, most facilitators are improving but a few run inefficient meetings. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed..
Why this is the answer
The project manager should praise the team for their self-organization and growth, as this reinforces agile principles and encourages continued development. Then, working one-on-one with specific facilitators who are struggling allows for targeted coaching and improvement without undermining the team's autonomy or the practice of rotating facilitators. Returning to the Scrum Master as facilitator negates the team's self-organizing efforts. Asking some facilitators to stop is demotivating and goes against the principle of continuous improvement. Retraining everyone is inefficient when only a few need help and could be seen as micromanaging, rather than fostering self-organization.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed