In standups a team member has given the same update for five days. That task is on the critical path and now risks delaying the schedule. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Ask the team member if there is an impediment, and help to remove the blockers..
Why this is the answer
The project manager's primary role in an agile environment is to facilitate and remove impediments. If a task is stalled, especially one on the critical path, the most effective action is to directly address the issue with the team member. There might be a blocker they are unable to resolve alone. Asking about impediments and offering support aligns with servant leadership and problem-solving. Informing the sponsor is premature without understanding the root cause or attempting to resolve it. Reassigning the task or adding resources without understanding the problem could be inefficient, demotivating, or ineffective if the underlying issue isn't addressed.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed