Knowledge sharing is a priority on a complex technology project with many team members. During execution, the project manager receives many complaints that team members are overloaded with knowledge-sharing emails that are useful but unmanageable. What should the project manager do to address this?
Choose an answer
Tap an option to check your answer.
Correct answer: Establish a pull communications method to access knowledge repositories and lessons learned..
Why this is the answer
The project manager should establish a pull communications method. This approach allows team members to access information when they need it, rather than being inundated with unsolicited emails. Knowledge repositories and lessons learned databases are examples of pull communication, as individuals actively retrieve the information they require. This reduces information overload while ensuring valuable knowledge is still available. Establishing an unofficial method is risky and can lead to inconsistent information and lack of accountability. An interactive method, while beneficial for discussion, might not solve the overload issue if not structured properly. A push communications method, like the current email system, is precisely what is causing the overload, as information is sent out regardless of the recipient's immediate need or capacity.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed