Mid-project the lead design programmer accepted a job at a competitor and left, and a milestone is approaching. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Consult the risk response plan..
Why this is the answer
The correct answer is to consult the risk response plan. The departure of a key team member, especially a lead programmer, is a foreseeable event that should have been identified as a risk during planning. The risk response plan would outline pre-defined strategies for mitigating the impact of such an occurrence, such as cross-training, identifying backup resources, or a communication plan. Updating the resource calendar is a subsequent action, not the immediate first step; it reflects the change but doesn't solve the problem. Issuing a request to the change control board (CCB) is premature; the CCB handles proposed changes to the project baseline, and while a schedule or cost change might result, the immediate action is to address the risk. Assigning tasks to another team member without consulting the risk plan might be a viable solution, but it's an action within a risk response, not the initial step to determine the best course of action.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed