On a bridge construction project a regulatory stakeholder requested adding a branch to the bridge design. The project manager prepared a change request, which the change control board (CCB) approved. What should the project manager do now?
Choose an answer
Tap an option to check your answer.
Correct answer: Evaluate the necessary updates to the project management plan..
Why this is the answer
After a change request is approved by the Change Control Board (CCB), the project manager's immediate next step is to evaluate the necessary updates to the project management plan and its subsidiary plans and baselines. This ensures that the project documentation accurately reflects the approved change and that all impacts are properly assessed and integrated. Simply notifying the team or the stakeholder is premature without first understanding the full implications for the project plan. Adding the new branch to the engineering design is an execution step that occurs after the planning documents have been updated and approved, not immediately after CCB approval.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed