On a hybrid software project with four sprints, at the end of sprint three the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Fast track the project.
Why this is the answer
The project is behind schedule because the Earned Value (EV) of US$500,000 is less than the Planned Value (PV) of US$550,000. This indicates that less work has been completed than planned by this point. To bring the project back on track, the project manager should consider schedule compression techniques. Fast-tracking involves performing activities in parallel that would normally be done in sequence, which can accelerate the project without increasing resources. Adjusting the budget is incorrect; the issue is schedule, not cost. Introducing a float is incorrect; float is a characteristic of the schedule, not an action to correct a delay. Adjusting the project timeline is too vague; while the timeline needs adjustment, "fast track" is a specific, actionable technique to achieve that adjustment.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed