On a large construction project the plan specified a cloud-based system using a high-speed internet server because most team members work virtually. Management now insists on switching to a conventional dial-up system to cut operating costs. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Assess the impact of this decision and communicate the findings with management..
Why this is the answer
The project manager's primary responsibility is to act in the best interest of the project. A sudden, significant change like switching from cloud-based high-speed internet to a dial-up system will likely have substantial impacts on project scope, schedule, cost, quality, and risk, especially given the virtual nature of the team. Therefore, the project manager must first assess these impacts thoroughly. This assessment will provide objective data to communicate to management, allowing for an informed decision. Agreeing without assessment is irresponsible. Replacing virtual team members is not a direct solution to the connectivity issue and might introduce new problems. Asking for a different project manager avoids the responsibility of managing the current situation.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed