On a mobile application project, an experienced team member has started missing deadlines, and these delays will affect implementation. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet with the team member to understand their concerns and issues.
Why this is the answer
The project manager's first step should be to meet with the team member to understand the root cause of the missed deadlines. This direct, one-on-one communication respects the individual and allows for a private discussion to uncover any personal or professional challenges affecting performance. Assigning another resource without understanding the problem might not solve the underlying issue and could be an inefficient use of resources. Checking with the functional manager is a secondary step, potentially useful if the direct conversation doesn't yield a clear understanding or if the issue is systemic. Holding a team meeting for motivation is too general and doesn't address the specific problem with one team member; it might also embarrass the individual.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed