On an agile project using the Scrum framework, the team asks which artifact replaces the traditional project schedule. How should the project manager answer?
Choose an answer
Tap an option to check your answer.
Correct answer: Product backlog and scrum board.
Why this is the answer
The correct answer is Product backlog and scrum board. In Scrum, the Product Backlog serves as the ordered list of all known features, functions, requirements, enhancements, and fixes that constitute the changes to be made to the product in future releases. It is dynamic and evolves as the product and environment change, acting as a high-level, prioritized "to-do" list for the entire project. The Scrum Board (or task board) visually represents the work items from the Sprint Backlog as they move through different stages (e.g., To Do, In Progress, Done) during a sprint, providing a real-time view of the team's progress for that specific iteration. The other options are incorrect because: Product roadmap and sprint backlog: While a product roadmap provides a high-level strategic overview, it's not a detailed operational schedule. The sprint backlog is only for a single sprint. Sprint backlog and scrum board: The sprint backlog only covers one sprint, not the entire project. Sprint plan and product roadmap: The sprint plan is the output of sprint planning, not an artifact itself that replaces the overall schedule.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed