On day four of a 15-day sprint, a Scrum team reviews the burndown chart (shown). What should the team do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Continue with the sprint work as planned and keep monitoring.
Why this is the answer
The burndown chart shows the team is slightly ahead of schedule, but it's only day four of a 15-day sprint. This early in the sprint, minor fluctuations are normal, and the current progress doesn't indicate a significant deviation that requires immediate corrective action. The team should continue executing the sprint backlog as planned and monitor the burndown chart regularly. Asking the product owner to cut stories is premature; the team is currently ahead, not behind. Selecting additional stories is also premature and could lead to overcommitment or quality issues later in the sprint. While there's a buffer, it's too early to assume extra capacity; this buffer could be absorbed by unforeseen complexities or issues as the sprint progresses. The most appropriate action is to maintain the current course and continue monitoring.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed