Prior to launching a new release, a stakeholder reports: a major corporate rebrand tied to the launch is delayed by three weeks; development process improvements will be ready in four weeks; and the company is preselling the updated product with a release date next week. What should the project manager recommend to the sponsor?
Choose an answer
Tap an option to check your answer.
Correct answer: Postpone the rebrand and release the product now to deliver the realized improvements and meet sales commitments.
Why this is the answer
The project manager should recommend postponing the rebrand and releasing the product now. This option prioritizes delivering the product to customers as promised by sales and capitalizing on the presales. The rebrand, while important, is a separate initiative that can be decoupled from the product release to avoid further delays and maintain customer trust. Delaying the release until the marketing or process improvement issues are resolved would break commitments to customers and negate the benefit of presales. Asking sales to inform customers of a delay is a reactive measure that damages customer relations and should be a last resort.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed