Team members are not engaged or committed to the project's success. What should the project manager do to address this?
Choose an answer
Tap an option to check your answer.
Correct answer: Call each team member to understand their perspective, then convene the whole team to discuss a solution.
Why this is the answer
The project manager should first understand the root cause of the disengagement by speaking individually with team members. This allows for a safe space for them to express concerns without peer pressure. Following this, a team meeting can be held to collaboratively discuss solutions, fostering a sense of ownership and commitment. Releasing the team is a drastic and costly measure that doesn't address the underlying issues. Warning emails are counterproductive and will further decrease morale and trust. Accepting the situation is passive and will lead to project failure.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed