Team members start work at different times each day, resulting in short overlaps and reduced team interaction and effectiveness. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Ask the team to define a team charter and agree on core working hours..
Why this is the answer
The best approach is to ask the team to define a team charter and agree on core working hours. This empowers the team to collaboratively establish their own operating guidelines and expectations, fostering commitment and buy-in. A team charter often includes agreements on communication, decision-making, and working hours, directly addressing the issue of reduced interaction. Telling team members to start earlier is a top-down command that may be met with resistance and doesn't address the underlying issue of team autonomy. Assigning overlapping work periods without team input is similar; it's prescriptive and can lead to resentment rather than improved collaboration. Requiring the entire team to start at the same time is also a directive that might not be feasible or desirable for all team members and bypasses the opportunity for team self-organization.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed