Team working hours were agreed at project start, but later one member says those hours no longer work due to personal commitments. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Change the duration of iterations to deliver more value.
Why this is the answer
The correct answer is to change the duration of iterations to deliver more value. When a team member's availability changes, adjusting iteration length can help maintain a sustainable pace and ensure deliverables are still met. This agile approach focuses on adapting to team capacity while continuing to deliver value. Validating iteration goals with the customer is a good practice, but it doesn't directly address the team member's personal commitments or the impact on work capacity. Inviting the customer to daily meetings is also a good practice for transparency but doesn't resolve the core issue of reduced team availability. Helping the team redefine the MVP might be necessary if the scope is too large for the available capacity, but adjusting iteration duration is a more immediate and flexible response to a change in working hours.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed