The company is experienced with predictive projects and the PMO introduced iterative tools into the project framework. After successfully using these tools, the PMO asks the project manager to identify the benefits they brought. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project..
Why this is the answer
The project manager should conduct reviews with stakeholders to discuss the potential benefits. This directly addresses the PMO's request to identify benefits and leverages stakeholder input, which is crucial for understanding the real-world impact of the new tools. Stakeholders, including team members and users, are best positioned to articulate how the iterative tools improved their work or the project outcomes. The other options are less direct or premature. Determining data and targets (A) is part of initial planning, not benefit identification after use. Updating the communications plan (B) is a supporting activity, not the core task of identifying benefits. Preparing a status report (C) is a reporting mechanism, but doesn't involve the active identification and discussion of benefits with those who experienced them.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed