The company requires everyone to take vacation before year-end, which may affect the project timeline. How should the project manager respond?
Choose an answer
Tap an option to check your answer.
Correct answer: Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.
Why this is the answer
The project manager's role involves proactive problem-solving and collaboration. Agreeing on a vacation schedule with functional management and team members allows for a negotiated solution that balances company policy with project needs, minimizing negative impacts. Submitting a formal request to senior management to reverse a company-wide decision is unlikely to be effective and is an escalation without attempting a collaborative solution first. Adjusting the project timeline without negotiation is a passive approach that could lead to unnecessary delays or missed objectives. Discussing the plan and recording changes is a necessary step, but it's reactive; the project manager should first attempt to influence the outcome to protect the project.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed