The IT team that validates and releases the product is delaying releases because of other priorities. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Work with the IT team to prioritize the validation and release of the new features..
Why this is the answer
The project manager should work collaboratively with the IT team to integrate the validation and release of new features into their existing priorities. This approach fosters cooperation and helps find a mutually agreeable solution, ensuring the project's needs are met without causing undue disruption to the IT team's other critical tasks. Releasing features only when the IT team is able to validate them is passive and doesn't address the root cause of the delay. Escalating to management might be necessary if collaboration fails, but it should not be the first step as it can create conflict. Requesting immediate release and post-release validation is risky, as it bypasses critical quality gates and could lead to defects in production.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed