The marine authority will not issue the work permit until certain environmental reinforcement work is completed, but that reinforcement is not in the project scope. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Start the organization’s change control process via a change request..
Why this is the answer
The correct answer is to start the organization’s change control process via a change request. The environmental reinforcement work is a new requirement essential for obtaining the work permit, meaning it directly impacts the project's ability to proceed and achieve its objectives. Since it's outside the original scope, it constitutes a change. The formal change control process ensures that such changes are properly documented, evaluated for impact (cost, schedule, resources), approved by relevant stakeholders, and integrated into the project plan. Raising the issue and updating the progress report is insufficient because it doesn't address the underlying problem or provide a solution. Contacting an officer to verify necessity might be part of gathering information but doesn't resolve the scope change. Holding a meeting to revise the WBS is premature; a WBS revision is an outcome of an approved change, not the initial step for an out-of-scope requirement.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed