The PMO is trying to adopt an adaptive approach and has asked a project manager to use adaptive tools. A previous attempt failed. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan.
Why this is the answer
The project manager should conduct individual interviews with key stakeholders to understand their concerns and then prepare a communications management plan. The previous attempt to adopt adaptive tools failed, indicating a potential lack of understanding, buy-in, or effective communication among stakeholders. By interviewing stakeholders, the project manager can identify specific pain points, resistance, or misunderstandings. A well-crafted communications management plan, based on these insights, can then address these concerns proactively, build consensus, and facilitate a smoother adoption of adaptive tools. Preparing a change request for a new framework (option A) is premature without understanding the root causes of the previous failure. Hiring an external firm (option C) is an expensive and potentially unnecessary step before internal analysis. Advising the PMO against the change (option D) is not a proactive or problem-solving approach; the PMO has already indicated a desire to adopt adaptive tools.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed