The product owner, a newly appointed VP, refuses to engage the CTO despite functional requirements that conflict with the CTO's strategy. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Influence the product owner to consider the engagement needed from other stakeholders..
Why this is the answer
The project manager's role is to facilitate collaboration and ensure project success. Influencing the product owner to engage the CTO directly addresses the conflict and leverages the product owner's authority to resolve it. This proactive approach prevents future issues and aligns the project with organizational strategy. Advising the CTO directly bypasses the product owner and could undermine their authority, potentially escalating the conflict rather than resolving it collaboratively. Continuing to build the backlog without addressing the conflict ignores a critical risk that could lead to significant rework or project failure. Reviewing OPAs is a good practice but doesn't directly resolve the immediate stakeholder conflict; it's a supporting activity, not the primary solution.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed