The project manager is tailoring artifacts for a unique project that differs from the organization's usual projects. Who should decide which artifacts to use?
Choose an answer
Tap an option to check your answer.
Correct answer: The project manager and project management team should select the appropriate artifacts for this specific project..
Why this is the answer
The project manager, in collaboration with the project management team, is responsible for tailoring the project management process and selecting appropriate artifacts. This ensures the chosen artifacts are suitable for the project's unique characteristics, complexity, and stakeholder needs. While organizational standards provide a baseline, they may require adaptation for non-standard projects. Project stakeholders provide input but typically do not make direct decisions on artifact selection. The project sponsor approves the project charter and significant changes but delegates the detailed planning and artifact selection to the project manager and team.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed