The project manager realizes the team is unlikely to finish system development before the scheduled testing start date due to technical complexity. What should the project manager do before informing the client at the regular progress meeting?
Choose an answer
Tap an option to check your answer.
Correct answer: Work with the project team to evaluate the potential delay..
Why this is the answer
Before communicating a potential issue to stakeholders, a project manager should always gather and analyze information. Working with the project team to evaluate the potential delay allows for a thorough understanding of the situation, including its root causes, impact, and possible mitigation strategies. This enables the project manager to present a comprehensive update to the client, rather than just an unquantified problem. Asking the project sponsor to notify the client is abdication of responsibility. Refraining from disclosure is a failure of transparency and risk management. Telling the client about a possibility without understanding its full scope or solutions can cause unnecessary alarm and damage trust.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed