The project sponsor keeps changing priorities for modular work packages. The team runs three-week sprints and is frustrated by daily scope changes. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle..
Why this is the answer
The correct answer is to meet with the sponsor. Frequent, unmanaged scope changes during a sprint disrupt the team's focus, reduce productivity, and undermine the sprint goal. The project manager must address the root cause by discussing the impact of these changes with the sponsor and reinforcing the importance of stable sprint backlogs for effective agile delivery. Shortening the sprint to match reprioritization intervals is reactive and doesn't solve the underlying issue of unstable priorities; it merely accommodates them, potentially leading to even more fragmented work. Holding a meeting with the team is good for gathering input but doesn't directly resolve the external pressure from the sponsor. Switching to Kanban might offer more flexibility but doesn't address the core problem of constantly shifting priorities, which would still negatively impact flow and predictability even in a Kanban system.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed