The project sponsor requested a trend analysis of all risks monitored over the past 12 months. What should the agile project manager provide?
Choose an answer
Tap an option to check your answer.
Correct answer: Extract this from the project risk register tracking tool and issues log.
Why this is the answer
The project risk register and issues log are the primary tools for tracking and monitoring risks and issues throughout a project. A trend analysis of risks over the past 12 months would involve reviewing the historical data contained within these documents to identify patterns, frequencies, and impacts of risks. The contract document outlines project agreements but does not contain risk tracking data. Organizing a brainstorming meeting would generate new risks, not analyze past trends. While an annual project report might summarize some risk information, the detailed data needed for a trend analysis resides in the risk register and issues log.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed