The project team has raised a significant issue: several stakeholder requirements conflict. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Negotiate a shared agreement with the affected stakeholders about the requirements..
Why this is the answer
Negotiating a shared agreement with affected stakeholders is the most effective approach because it directly addresses the conflict at its source. This involves facilitating discussions to understand each stakeholder's perspective, identify common ground, and find a mutually acceptable solution that satisfies the most critical needs while managing expectations. Escalating to the PMO is premature; the project manager should first attempt to resolve issues at their level. Allowing the team to decide is inappropriate as stakeholders own the requirements, not the team. Deferring resolution will only exacerbate the problem and likely lead to rework or project failure later.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed