The team delivers incrementally in an iterative project, but stakeholders claim value delivered has declined over time even though completion is on track. How should the project manager respond?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the value-delivery schedule with the team to determine why value is declining, implement fixes to stabilize delivery, and communicate the corrective actions..
Why this is the answer
The correct response is to review the value-delivery schedule with the team, determine the root cause of the decline, implement corrective actions, and communicate these changes. This proactive approach addresses the stakeholders' concerns directly by investigating the problem and taking steps to resolve it, aligning with the project manager's responsibility to ensure value delivery. Telling stakeholders that progress is measured by completed requirements against the schedule ignores their concern about declining value, which is a critical aspect of iterative projects. Explaining that delivered value depends on resources and potential gains is a general statement that doesn't address the specific problem of declining value in this project. Informing stakeholders that declining value is expected because the backlog is prioritized for highest business value first is a common misconception; while initial increments often deliver the highest value, subsequent increments should still provide significant, consistent value, and a continuous decline signals a problem that needs investigation.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed