The team is not delivering committed work: Kanban cards are not moving and the burndown chart shows slow sprint progress. What should the agile project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet individually with team members who are slow to deliver tasks..
Why this is the answer
Meeting individually with team members who are slow to deliver tasks is the most appropriate first step. This allows the agile project manager to understand the root causes of the delays, which could include skill gaps, impediments, or personal issues, without immediately escalating or making broad team-level changes. It fosters a supportive environment and helps identify specific areas for coaching or intervention. Adjusting the WIP limit might be a solution, but it's premature without understanding why work isn't moving. Simply changing the limit without addressing underlying problems won't resolve the core issue. Considering alternative performance metrics doesn't address the current problem of stalled work. Discussing performance with senior leadership is an escalation that should only occur after attempting to resolve the issue directly with the team members involved.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed