The team uses a hybrid delivery framework. During execution, a new compliance requirement is discovered that must be delivered before any other requirements. How should the project manager handle this situation?
Choose an answer
Tap an option to check your answer.
Correct answer: Collaborate with the compliance team member to review and prioritize the requirement's delivery..
Why this is the answer
In a hybrid framework, adaptability and collaboration are key. The project manager should immediately collaborate with the compliance team member to understand the new requirement's urgency, impact, and dependencies. This allows for a timely review and prioritization, ensuring the project remains compliant while minimizing disruption. Simply adding it to the backlog without discussion defers a critical issue. Including the compliance lead in the stakeholder list is a good practice but doesn't address the immediate prioritization need. Forcing it into the current sprint without proper assessment could destabilize the sprint and potentially lead to quality issues or missed commitments.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed