Two linked subprojects start; a contractor agreed to biweekly status reports and weekly integration meetings but stops attending and submitting reports, saying those tasks take too much time. How should the project manager respond?
Choose an answer
Tap an option to check your answer.
Correct answer: Assess the situation as a risk and reach out to the contractor to check the origin of this resistance..
Why this is the answer
The best first step is to assess the situation as a risk and engage the contractor to understand their concerns. This proactive approach allows the project manager to identify the root cause of the resistance, which could be anything from workload issues to misunderstandings about the value of the reports. Understanding the problem is crucial for finding a viable solution and maintaining a productive working relationship. Filing a claim is premature and escalatory; it should be a last resort after attempts at resolution fail. Simply reminding the contractor of their commitment is unlikely to resolve the underlying issue and may be perceived as unhelpful. Compromising by eliminating reports without understanding the impact or exploring alternatives could lead to a loss of critical information and project control.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed